• Baslow Environment Projects Limited has applied to the Environment Agency for a licence to take water from the River Derwent at Baslow Weir to generate hydro-electric power.
• The plan is for a new channel around the west end of the weir housing a 50-kilowatt screw turbine; the weir itself would not be altered.
• All the water would be returned to the Derwent a short way downstream.
• Written comments should be sent to the Environment Agency by today, Thursday 29 October, quoting reference NPS/WR/047170.

A proposal to generate electricity from the River Derwent at Baslow has reached the final day of its public consultation. The Environment Agency published notice on 1 October of an application by Baslow Environment Projects Limited, which Companies House lists as a registered society, for a full water abstraction licence at Baslow Weir. The water would drive a 50-kilowatt screw turbine in a new channel at the west end of the weir before flowing back into the river. Anyone wishing to comment has until today to write to the agency by email or post.

Photo: The weir on the River Derwent at Baslow in autumn 2007. Roger Temple / Geograph via Wikimedia Commons, CC BY-SA 2.0

Source: Environment Agency (GOV.UK notice); Companies House. Linked: Environment Agency.

Baslow Environment Projects Limited has applied to the Environment Agency for a full licence to abstract water from the River Derwent at Baslow Weir, according to a public notice published on GOV.UK on 1 October. The water would be used to generate hydro-electric power.

The notice says the scheme would create a channel around the west end of Baslow Weir, where a screw turbine with an output of 50 kilowatts would be installed. The existing weir would not be modified.

A screw turbine with an output of 50 kilowatts

The application seeks to take up to 16,920 cubic metres of water an hour, or 406,080 cubic metres a day, throughout the year. All of the water taken would be returned to the Derwent a short distance downstream of the abstraction point.

Companies House lists Baslow Environment Projects Limited as a registered society, a type of organisation recorded on the Financial Conduct Authority's Mutuals Public Register.

The existing weir would not be modified

The Environment Agency is advertising the application under the Water Resources Act 1991. Written representations, quoting the applicant's name and reference NPS/WR/047170, should be sent by Thursday 29 October 2026, the notice says.

Comments can be emailed to PSC-WaterResources@environment-agency.gov.uk or posted to the Environment Agency, Permitting and Support Centre, Water Resources Team, Quadrant 2, 99 Parkway Avenue, Sheffield S9 4WF. The agency says people can arrange to see the application documents by email or by calling 03708 506 506, which also offers advice on making a representation.

Written representations should be sent by Thursday 29 October

More from the Morning edition, Thu 29 Oct 2026 →